What are the steps involved in building your GHI Conservatory? Please click on the images for full-size photos.
Foundations are excavated for the pouring of mass concrete.
Brick footings are taken up to damp proof course level, damp proof membrane is laid on top of under floor insulation and concrete floor is laid to float finish.
Brick and blockwork is laid to dwarf wall dimensions.
Conservatory is erected and glazed. Internal plastering is started.
Second fix electrics and floor screeds are completed.
Conservatory complete. Another successful installation